↑ TopSchedule a call
PUBLIC · Updated Oct 17, 2026

Project Lucky 7

Site control available today, with a pathway to a $3.1B data center campus.
±323 acres outside Cheyenne with three interstate gas pipelines crossing it.

Aerial view of the option parcel: the gas pipeline corridor (three interstate lines) crossing it, the access road corridor off Harriman Road, and the existing 34.5 kV distribution line
Laramie County, WyomingOn I-80, ~20 minutes west of Cheyenne

Assumptions

Three cases, each with its own buildable acres, density and cost per MW.
Pick one, and everything recalculates.

Base case assumptions

Buildable acres and density vary with the end user's site plan and building plan.

Buildable acres
Density (MW per acre)
All-in build cost per MW
Excludes chips and GPUs.

Density moves capacity most

  • Across the three cases, density swings 50% (1.0 to 1.5 MW per acre); buildable acres swing 8% (240 to 260).
  • Density is MW of data center load per buildable acre. 1.0 MW per acre is the lowest we've heard from market participants; the top case uses 1.5 MW per acre.
  • Public campuses pencil at roughly 0.9 to 2 MW per gross acre: Meta's Louisiana campus, ~2 GW on 2,250 acres (~0.9); Crusoe's Abilene campus, 1.2 GW on ~1,100 acres (~1.1); JLL puts 1 GW-plus campuses at 500 to 800 acres (1.25 to 2.0). Our cases are stated per buildable acre; on 323 gross acres the top case reads ~1.2 MW per gross acre.

From 323 acres to the three cases

Pre-survey site shading plan, ±323 acres, Laramie County, WY: buildable area about 264 acres (152 + 112), pipeline corridor easement about 31.5 acres, access road strip about 24 acres. Approximate.
  • ±323 acres surveyed, less the access road strip (~24) and the pipeline corridor easement (~31.5) leaves ~264 buildable on the pre-survey shading plan.
  • The cases sit below that on purpose: 260 is the plan, 250 the base, 240 the low case, leaving room for setbacks, drainage, geotech and topography.
  • All estimated until the ALTA survey (due Nov 4) and the stamped exhibit. Title and survey are on order.

Cost per MW

  • All-in to build, excluding chips and GPUs: $9M, $10M and $11M, with $10M the base. A lower cost means a smaller tax savings, so the conservative case uses the lowest.
  • Source: Cushman & Wakefield, Data Center Development Cost Guide 2026: $8.9M–$23.3M per MW across the U.S. and Canada, with Cheyenne in the lower-cost third of its 38 markets.

Capacity

Project cost: capital investment

The Timeline

Rezoning, Gas and Grid

  • Rezoned Q1 2027. County Commissioners vote February 2, 2027. Agricultural to PUD, which allows data center use.
  • 11–13 months to gas at the site. The clock starts at a signed agreement and funded deposit.
  • Grid at campus scale in 5+ years. Application filed with the utility.

Swipe the chart to see the full timeline →

Q4 2026Q1 2027Q2 2027Q3 2027Q4 2027Q1 2028
Rezoning Laramie County · running now
Oct 5 · Commissioners briefing
Nov 6 · PUD submittal
Jan 14 · Planning Commission
Feb 2 · Commissioners vote: rezoned
Gas buyer-triggered
Buyer signs and funds (illustrative; the buyer sets this date)
11–13 months to gas at the site
Grid campus scale
5+ years →

Planned dates; the county sets hearing dates. A local planning team and local counsel are working it with county staff.

Two Unanimous County Approvals

For gas-powered data center campuses in 2026

January
A 1.8 GW data center campus, scalable to 10 GW, with a co-located 2.7 GW behind-the-meter gas plant, about 8 miles south of Cheyenne.
September
A PUD rezone for an 1,835-acre, 480 MW gas-powered campus, about 12 miles south of Cheyenne.

Different developers, different sites, the same answer.

What the County Gains

Property Tax
a year, first year
County Tax Base
added to the county's entire tax base
Construction
jobs at peak
Estimate, scaled from a county precedent
Permanent
jobs ongoing
Estimate, scaled from a county precedent

What the Site Offers

Site Control

Ready to assign today.

  • Purchase option, freely assignable without seller consent.
  • Executed and recorded, September 2026.
  • The buyer closes directly with the landowner.
  • Open to term sheets anytime.

Gas · 11–13 Months

A mainline corridor, not a single-pipe site.

  • Capacity indicated in writing by three interstate operators.
  • Three interstate operators, three separate lines — gas supply options for the buyer.
  • Four interstate lines in the corridor — three cross the parcel.

Grid · 5+ Years

Construction power nearby; campus scale later.

  • 34.5 kV distribution tap about 1,000 ft from the parcel, for construction power and station service.
  • Application filed with the serving utility.
  • Large-load study queue scheduling into Q2 2027.
  • Construction begins once the end user signs service, interconnection and generation agreements.

Wyoming Tax Savings

Initial Build
Each Refresh
new hardware, every 4–5 years

The Wyoming exemption

  • Wyoming exempts qualifying data center equipment from sales and use tax, for data centers that meet the state's investment thresholds.
  • Servers, networking gear and the supporting infrastructure that goes into a qualifying facility are not taxed on purchase.
  • Qualification is based on investment size, with thresholds starting at $5M in capital infrastructure and $2M in qualifying equipment.
  • These figures estimate what that saves a buyer on this site. Confirm with tax counsel.

How the estimate works

  • Assumes each case's cost per MW ($9M, $10M or $11M) and ~60% in qualifying equipment: roughly $338K, $375K or $413K of savings per MW, applied to the MW in the case shown.
  • It moves with the case shown. A buyer's actual build plan sets the real number.

Data Centers in Cheyenne

Data centers in and around Cheyenne:

10operating
5being built
10planned
  • Meta is building in Laramie County: $800M, 715,000 sq ft on a 960-acre parcel south of Cheyenne, online 2027.
  • On a transcontinental fiber route, about 100 miles from Denver.

Data center counts and fiber per Cheyenne LEADS.

Interested in more details about this project?

Operators, capacity position and the full diligence package are shared under NDA.

Sign NDA for full details
Terra Firma / Lucky 7
John Giordani · Principal
(415) 577-9311 Schedule a call